“There is now a big shift coming, with new clean technologies like batteries and synchronous compensators able to provide grid system services reliably, at low cost and without relying on fossil fuels.
“But many of these projects are stuck in the queue waiting to connect. If they’re going to support the system, NESO and the monopoly network owners need to treat them as a priority and get them connected now.
“For clean energy projects in the south west, things might get worse before they get better.”
NESO and NGED could have explored alternatives to a total shutdown, industry sources say.
Constraints
A spokesperson for Ecotricity, which had its Galsworthy Wind Farm and Bulkworthy Solar farm curtailed, asked: “Did they exhaust all technical options available before they turned us off?”
An NGED spokesperson said options assessed were “not considered suitable within the relevant timeframe”.
The financial blow to Derril Water is more severe than for larger corporates, who are cushioned from the effect of the shutdown by other generation assets.
When larger renewables projects connected directly to the transmission grid are curtailed, they are paid compensation, but smaller generators connected to distribution grids are not.
These “constraints payments”, mostly to Scotland’s big wind farms, are eye-watering: a total of £2.7 billion for the financial year from April 2024 alone.
Challenge
These payments, the curtailment of distribution-connected solar farms, and the years-long queues for connections to both transmission and distribution networks, are all part of the same problem.
Electricity companies have failed to invest fast enough to facilitate renewable generation, and government regulators have failed to make sure they do.
In the twentieth century the grid sent electricity out to users from large, centralised power stations. In the twenty-first, the system needs to become a two-way process that gathers electricity from a much larger number of much smaller generators, and facilitates local sharing and use efficiencies.
This has become more pressing as the climate crisis has deepened. And big up-front investments are needed.
As for the low-voltage distribution networks, a report by the MCS Foundation and Regen argued that upgrading them to prepare for increased demand is a “major challenge”. The distribution companies’ business plans for 2023-28 are not good enough, the report warned.
Connections
The government’s own National Infrastructure Commission last year warned that “a step change in the approach” to electricity distribution reform is needed.
Distribution grids would need £37 billion to £50 billion of investment between 2025 and 2050, double the rate envisaged by Ofgem, the electricity regulator.
Things are changing – but not fast enough. By carving NESO out of National Grid in 2024, the government took a first step to reversing decades of privatisation driven by neo-liberal dogma.
It implicitly recognised that electricity grid reform could not be left to profiteering private companies.
NESO last year tackled one of the biggest scandals, by reforming the queue for grid connections. But we are still a long way from a grid that can deal with the climate emergency.
Perilous
The regulators and companies talk about community energy projects being part of the solution, but don’t act as though they are.
Matt Vickers of Community Energy England said that the problems at Derril Water showed how far there is to go. “Grid companies need not only to provide connections, but to treat communities as strategic partners.”
The more that communities take electricity provision in to their own hands, the better. Derril Water shows that leaving it to profiteers and too-timid regulators is perilous.
The full text of this investigation is on People & Nature.